Traffic Alert – April 14, 2022

Posted on April 14, 2022 by - Traffic Alerts

Traffic Alert – April 14, 2022

On or about the night of 4/19/22, the Southbound Inner/Express Exit Ramp at Interchange105 will be closed. This ramp will remain closed for approximately 8 months. The Southbound Outer/Local ramps at Exit 105 will remain open. Inner/Express lane motorists who wish to get off at Interchange 105 will be detoured down to Interchange 102.

On or about the night of 4/19/22, the Northbound Inner/Express Entrance Ramp at Interchange 105 will be closed. This ramp will remain closed for approximately 8 months. The Northbound Outer/Local Entrance ramps at Interchange 105 will remain open.

Monthly Project Update – March 29, 2022

Posted on March 29, 2022 by - Project Updates

Monthly Project Update – March 29, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of April 25, 2022.

FOUR WEEK SCHEDULE AS OF MARCH 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of April 4, 2022, work will begin on Str. 106.4NO with the installation of temporary working platforms.
  • During the week of week of April 18, 2022, the closure of the southbound inner exit lanes will begin.  The demolition of Str. 106.4I will immediately follow. Detours can be found on this page: https://www.gspexit105.com/detours/

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of April 18, 2022, work will begin to close the northbound inner entrance lanes.  The demolition of Str. 106.5NO will immediately follow. Detours can be found on this page: https://www.gspexit105.com/detours/

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

Project Updates – January-March 2022

Posted on February 18, 2022 by - Project Updates

Project Updates – January-March 2022

Activities to date include:

  • Site Mobilization
  • Material Procurement

Expected Work Activities:

March 2022

  • Closure of Work Area D (Str. 106.5NO) Ramp to northbound Express Lanes
  • Closure of Work Area C (Str. 106.4I and Str. 106.4NO) Ramp from southbound Express Lanes
  • Demolition of Str. 106.5NO, Str. 106.4I and Str. 106.4NO