Archive Author: GSPI 105 Project Team

Traffic Alert – September 27, 2022

Posted on September 27, 2022 by - Traffic Alerts

Traffic Alert – September 27, 2022

Traffic Alert for October 03, 2022:

On or about the night of 10/03/22, Southbound Entrance Ramp will be closed starting at 10:00 PM and will remain closed until May 15, 2023.  This closure is required to replace the superstructure for Str. No.106.3I, Str. No.106.4NO and Str. No. 106.4A. Traffic will be detoured to Route 18 to Route 66 and or to GSP Northbound to Exit 109.  See the “Detours” page for more information on the new traffic patterns. Note that in the event of inclement weather, this work may be rescheduled for the following day 10/04/22 or later until completed. 

Monthly Project Update – September 30, 2022

Posted on September 27, 2022 by - Project Updates

Monthly Project Update – September 30, 2022

Garden State Parkway Exit 105 Monthly Update: 09/30/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of October 28, 2022.

FOUR WEEK SCHEDULE AS OF September 30, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of October 3, 2022, crews will install structural steel utilizing nightly lane closures.
  • During the week of October 10, 2022, crews will install shielding and overhang brackets. 
  • Concrete deck forms, sheer studs, and reinforcement steel will begin the 3rd and 4th week of October.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of October 3, 2022, crews will install deck forms and sheer studs.
  • During the week of October 10, 2022, crews will install reinforcement steel.
  • Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of October.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • On October 3, 2022, the South Bound Entrance Ramp will be closed.  It will remain closed until May 15, 2023.
  • Demolition Str. 106.4A will take place the 1st and 2nd weeks of October utilizing nightly ramp closures.
  • Demolition of Str. 106.3I will take place the 2nd and 3rd weeks of October utilizing nightly lane closures.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of October 3, 2022, work on the SBO to SBI (Local to Express) Crossover is schedule to begin.  Traffic will be shifted both on both the Local and Express lanes to facilitate the construction of this crossover ramp. Work is scheduled to take 4 weeks to construct.

Monthly Project Update – August 29, 2022

Posted on August 29, 2022 by - Project Updates

Monthly Project Update – August 29, 2022

Garden State Parkway Exit 105 Monthly Update: 08/29/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 12, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 7, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October 1, 2022, with the full closure of the South bound Entrance Ramp. The entrance ramp will be closed until all bridge structures are replaced.  This is anticipated to be completed May 15, 2022. Three detours will be in place.  See link for detours. 

South Bound Entrance Ramp, Ramp E1

  • On August 26, 2022, a watermain break was found in the South Bound Entrance Ramp.  The cause of the watermain break was not related to current construction activities.  The watermain was repaired and the roadway was restored.  

Monthly Project Update – August 2, 2022

Posted on August 2, 2022 by - Project Updates

Monthly Project Update – August 2, 2022

Garden State Parkway Exit 105 Monthly Update: 08/02/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 02, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 08, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of August 15, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the third week of August.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 22, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of August 29, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October of 2022.

Monthly Project Update – July 8, 2022

Posted on July 8, 2022 by - Project Updates

Monthly Project Update – July 8, 2022

Garden State Parkway Exit 105 Monthly Update: 07/08/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in August, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF July 08, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of July 11, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of July 18, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the last week of July.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of July 18, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of July 25, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

North Bound Entrance, Ramp E4

  • On July 5, 2022, a sinkhole was found in the North Bound Entrance Ramp.  The cause of the sinkhole was not related to current construction activities.  The sinkhole was filled in and a new drainage pipe was installed in this location. 

Monthly Project Update – May 31, 2022

Posted on May 31, 2022 by - Project Updates

Monthly Project Update – May 31, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of June 27, 2022.

FOUR WEEK SCHEDULE AS OF MAY 31, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of June 6, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 
  • During the week of June 13, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

Traffic Alert – May 25, 2022

Posted on May 17, 2022 by - Traffic Alerts

Traffic Alert – May 25, 2022

Traffic Alert for May 25, 2022:
On or about the evenings of 5/25/22 and 5/31/22, slowdowns will be utilized, from Northbound Exit 91 to Exit 105 between the hours of 10:00 PM and 5:00 AM, to facilitate the superstructure demolition of Str. No.106.5NO. Motorists should anticipate delays during this time.

Please Note: in the event of inclement weather, this work may be rescheduled for the following day 6/01/22 (or later) until completed.

Traffic Alert – May 20, 2022

Posted on May 13, 2022 by - Traffic Alerts

Traffic Alert – May 20, 2022

Traffic Alert for May 16, 2022:

On or about the evenings of 5/20/22 and 5/23/22, the Northbound Inner/Express Lanes will be closed at the toll plaza between the hours of 10:00 PM and 5:00 AM. This closure will facilitate the superstructure demolition of Str. No.106.4I. Traffic will be diverted to the Northbound Outer/Local Lanes.

NOTE: in the event of inclement weather, this work may be rescheduled for the following evening, 5/24/22, or later until completed. 

Traffic Alert – May 16, 2022

Posted on May 9, 2022 by - Traffic Alerts

Traffic Alert – May 16, 2022

Traffic Alert for May 16, 2022:

On or about the evening of 5/16/22, the Southbound Inner/Express Lanes will be closed at the 117.7 Crossover between the hours of 10:00 PM and 5:00 AM.  This closure is anticipated to take one to two evenings to complete. This closure will facilitate the superstructure demolition of Str. No.106.4I. Traffic will be diverted to the Southbound Outer/Local Lanes.

NOTE: in the event of inclement weather, this work may be rescheduled for the following evening, 5/18/22, or later until completed. 

Monthly Project Update – April 29, 2022

Posted on April 29, 2022 by - Project Updates

Monthly Project Update – April 29, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of May 25, 2022.

FOUR WEEK SCHEDULE AS OF APRIL 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of May 2, 2022, work will begin on Str. 106.4I to prepare for the removal of the superstructure.
  • During the week of week of May 16 and 23, 2022, crews will remove the superstructure (deck and beam) of Str. 106.4I. Weather permitting, this work is anticipated to take 6 shifts. 

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 9, 2022, work will begin on Str. 106.5NO to prepare for the removal of the superstructure.
  • During the week of May 23 and 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.