Monthly Project Update – May 31, 2022

Posted on May 31, 2022 by - Project Updates

Monthly Project Update – May 31, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of June 27, 2022.

FOUR WEEK SCHEDULE AS OF MAY 31, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of June 6, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 
  • During the week of June 13, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

Traffic Alert – May 25, 2022

Posted on May 17, 2022 by - Traffic Alerts

Traffic Alert – May 25, 2022

Traffic Alert for May 25, 2022:
On or about the evenings of 5/25/22 and 5/31/22, slowdowns will be utilized, from Northbound Exit 91 to Exit 105 between the hours of 10:00 PM and 5:00 AM, to facilitate the superstructure demolition of Str. No.106.5NO. Motorists should anticipate delays during this time.

Please Note: in the event of inclement weather, this work may be rescheduled for the following day 6/01/22 (or later) until completed.

Traffic Alert – May 20, 2022

Posted on May 13, 2022 by - Traffic Alerts

Traffic Alert – May 20, 2022

Traffic Alert for May 16, 2022:

On or about the evenings of 5/20/22 and 5/23/22, the Northbound Inner/Express Lanes will be closed at the toll plaza between the hours of 10:00 PM and 5:00 AM. This closure will facilitate the superstructure demolition of Str. No.106.4I. Traffic will be diverted to the Northbound Outer/Local Lanes.

NOTE: in the event of inclement weather, this work may be rescheduled for the following evening, 5/24/22, or later until completed. 

Traffic Alert – May 16, 2022

Posted on May 9, 2022 by - Traffic Alerts

Traffic Alert – May 16, 2022

Traffic Alert for May 16, 2022:

On or about the evening of 5/16/22, the Southbound Inner/Express Lanes will be closed at the 117.7 Crossover between the hours of 10:00 PM and 5:00 AM.  This closure is anticipated to take one to two evenings to complete. This closure will facilitate the superstructure demolition of Str. No.106.4I. Traffic will be diverted to the Southbound Outer/Local Lanes.

NOTE: in the event of inclement weather, this work may be rescheduled for the following evening, 5/18/22, or later until completed. 

Monthly Project Update – April 29, 2022

Posted on April 29, 2022 by - Project Updates

Monthly Project Update – April 29, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of May 25, 2022.

FOUR WEEK SCHEDULE AS OF APRIL 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of May 2, 2022, work will begin on Str. 106.4I to prepare for the removal of the superstructure.
  • During the week of week of May 16 and 23, 2022, crews will remove the superstructure (deck and beam) of Str. 106.4I. Weather permitting, this work is anticipated to take 6 shifts. 

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 9, 2022, work will begin on Str. 106.5NO to prepare for the removal of the superstructure.
  • During the week of May 23 and 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

Traffic Alert – April 14, 2022

Posted on April 14, 2022 by - Traffic Alerts

Traffic Alert – April 14, 2022

On or about the night of 4/19/22, the Southbound Inner/Express Exit Ramp at Interchange105 will be closed. This ramp will remain closed for approximately 8 months. The Southbound Outer/Local ramps at Exit 105 will remain open. Inner/Express lane motorists who wish to get off at Interchange 105 will be detoured down to Interchange 102.

On or about the night of 4/19/22, the Northbound Inner/Express Entrance Ramp at Interchange 105 will be closed. This ramp will remain closed for approximately 8 months. The Northbound Outer/Local Entrance ramps at Interchange 105 will remain open.

Monthly Project Update – March 29, 2022

Posted on March 29, 2022 by - Project Updates

Monthly Project Update – March 29, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of April 25, 2022.

FOUR WEEK SCHEDULE AS OF MARCH 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of April 4, 2022, work will begin on Str. 106.4NO with the installation of temporary working platforms.
  • During the week of week of April 18, 2022, the closure of the southbound inner exit lanes will begin.  The demolition of Str. 106.4I will immediately follow. Detours can be found on this page: https://www.gspexit105.com/detours/

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of April 18, 2022, work will begin to close the northbound inner entrance lanes.  The demolition of Str. 106.5NO will immediately follow. Detours can be found on this page: https://www.gspexit105.com/detours/

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

Project Updates – January-March 2022

Posted on February 18, 2022 by - Project Updates

Project Updates – January-March 2022

Activities to date include:

  • Site Mobilization
  • Material Procurement

Expected Work Activities:

March 2022

  • Closure of Work Area D (Str. 106.5NO) Ramp to northbound Express Lanes
  • Closure of Work Area C (Str. 106.4I and Str. 106.4NO) Ramp from southbound Express Lanes
  • Demolition of Str. 106.5NO, Str. 106.4I and Str. 106.4NO