Archive Author: GSPI 105 Project Team

Monthly Project Update – May 25, 2023

Posted on May 25, 2023 by - Project Updates

Monthly Project Update – May 25, 2023

Garden State Parkway Exit 105 Monthly Update: 05/25/23

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of June 12, 2023.

FOUR WEEK SCHEDULE AS OF May 25, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • This stage is considered substantially complete.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • This stage is considered substantially complete.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • The ramp was opened the evening of May 12, 2023.
  • This stage is considered substantially complete.

Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit

  • During the week of June 5, 2023, crews will install structural steel for the bridge deck.
  • During the week of June 12, 2023, crews will install temporary catch and stay-in-place forms. 
  • During the week of June 19, 2023, crews will begin to install rebar and deck forms.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the day of March 10, 2023, crews opened the crossover to traffic.

Monthly Project Update – April 28, 2023

Posted on April 28, 2023 by - Project Updates

Monthly Project Update – April 28, 2023

Garden State Parkway Exit 105 Monthly Update: 04/28/23

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of May 12, 2023.

FOUR WEEK SCHEDULE AS OF April 28, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • This stage is considered substantially complete.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • This stage is considered substantially complete.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of May 1, 2023, crews will install roadway subgrade and asphalt for the bridge approaches.
  • During the week of May 8, 2023, crews will install guide rail and roadway stripes in anticipation of the ramp opening.
  • The ramp is scheduled to be opened May 12, 2023.

Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit

  • During the week of May 1, 2023, crews will continue with demolition of piers and wing walls for Str. 106.4I.  
  • During the week of May 8, 2023, crews will begin with begin with the installation of drill and grout reinforcement steel for Str. 106.4I. 
  • During the week of May 15, 2023, crews will begin concrete repairs on Str. 106.4SO.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the day of March 10, 2023, crews opened the crossover to traffic.

Monthly Project Update – April 13, 2023

Posted on April 13, 2023 by - Project Updates

Monthly Project Update – April 13, 2023

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted during the week of May 8, 2023.

FOUR WEEK SCHEDULE AS OF April 13, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of March 6, 2023, work on Str. 106.4I was completed.
  • During the night of March 11, 2023, traffic was opened to the South Bound Inner Exit Ramp.
  • This stage is considered substantially complete.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 27, 2023, work on Str. 106.5NO was completed.
  • During the night of March 6, 2023, traffic was opened to the North Bound Inner Entrance Ramp.
  • This stage is considered substantially complete.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of April 10, 2023, crews installed parapet concrete at 106.4A and parapet reinforcement at Str. 106.3I.
  • During the week of April 17, 2023, crews will install parapet concrete at Str. 106.3I and perform spall repairs at Str. 106.4NO.
  • During the week of May 1, 2023, crews will install the parapet for Str. 106.4NO.
  • Asphalt is scheduled to be installed the week of May 8, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • During the week of April 17, 2023, demolition will begin with saw cutting and removing the superstructure for Str. 106.4I.
  • During the week of May 1, 2023, crews will begin demolition of piers for Str. 106.4I.  

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of March 6, 2023, crews finished installation of ground mounted signs.
  • During the day of March 10, 2023, crews opened the crossover to traffic.

Monthly Project Update – March 14, 2023

Posted on March 14, 2023 by - Project Updates

Monthly Project Update – March 14, 2023

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in April 2023.

FOUR WEEK SCHEDULE AS OF March 14, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of March 6, 2023, work on Str. 106.4I was completed.
  • During the night of March 11, 2023, traffic was opened to the South Bound Inner Exit Ramp.
  • This stage is considered substantially complete.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 27, 2023, work on Str. 106.5NO was completed.
  • During the night of March 6, 2023, traffic was opened to the North Bound Inner Entrance Ramp.
  • This stage is considered substantially complete.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of March 13, 2023, crews will install reinforcement steel at 106.4A and continue with form work at Str. 106.3I.
  • During the week of March 20, 2023, crews will install concrete for the deck of Str. 106.4A.
  • Closure pours for Str. 106.3I are scheduled for the week of March 27, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • During the night of March 11, 2023, traffic was close to the South Bound Outer Exit Ramp.
  • During the week of March 13, 2023, crews will begin demolition of Str. 106.4I and 106.4NO by removing the asphalt overlay.  

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of March 6, 2023, crews finished installation of ground mounted signs.
  • During the day of March 10, 2023, crews opened the crossover to traffic.

Monthly Project Update – February 01, 2023

Posted on February 1, 2023 by - Project Updates

Monthly Project Update – February 01, 2023

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of February 27, 2023.

FOUR WEEK SCHEDULE AS OF February 01, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 30, 2023, crews will install concrete for parapet for Str. 106.4I.
  • During the week of February 06, 2023, crews will install concrete for parapet for Str. 106.4NO.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The South Bound Inner Exit Ramp is scheduled to open the week of February 20, 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 06, 2023, crews will groove the concrete deck.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The North Bound Inner Entrance Ramp is scheduled to open the week of February 20, 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of February 03, 2023, crews will install structural steel at 106.4A.
  • During the week of February 6, 2023, crews will concrete for abutment reconstructions.
  • Erection of precast concrete units are scheduled for the week of February 13, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin late February of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • During the week of February 06, 2023, crews will roadway striping and move precast concrete construction barrier.
  • Opening of the crossover is schedule for the week of February 13, 2023.  

Monthly Project Update – January 13, 2023

Posted on January 13, 2023 by - Project Updates

Monthly Project Update – January 13, 2023

FOUR WEEK SCHEDULE AS OF January 13, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 16, 2023, crews will install reinforcement steel for parapet.
  • During the week of January 23, 2023, crews will install concrete for Parapet.
  • The South Bound Inner Exit Ramp is scheduled to open the month of February 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of January 23, 2023, crews will install guide rail.
  • During the week of January 30, 2023, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open the month of February 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of January 16, 2023, crews will install concrete for pier and abutments.
  • During the week of January 30, 2023, crews will remove forms in preparation for beam erection.
  • Erection of structural steel and precast concrete units are scheduled for the beginning of February.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • Opening of the crossover is schedule for the month of February 2023.  

Monthly Project Update – December 01, 2022

Posted on December 1, 2022 by - Project Updates

Monthly Project Update – December 01, 2022

FOUR WEEK SCHEDULE AS OF December 01, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of December 05, 2022, crews will install reinforcement steel.
  • During the week of December 12, 2022, crews will install concrete deck.
  • Concrete Parapet will be installed the 4th week of December.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of December 12, 2022, crews will install the concrete Parapet.
  • During the week of December 19, 2022, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open The first week of January 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of December 5, 2022, crews will install anchor bolts for bearings.
  • During the week of December 12, 2022, crews will drill and grout reinforcement steel.
  • Installation of pier forms at Str. 106.3I and Str. 106.4A will take place the rest of December.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of December 12, 2022, crews will install the asphalt surface course.  

Monthly Project Update – October 26, 2022

Posted on October 26, 2022 by - Project Updates

Monthly Project Update – October 26, 2022

Garden State Parkway Exit 105 Monthly Update: 10/26/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted approximately during the week of November 27, 2022.

FOUR WEEK SCHEDULE AS OF October 26, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of October 31, 2022, crews will install forms for the bridge deck.
  • During the week of November 7, 2022, crews will install Joints and shear studs.
  • During the week of November 14, 2022, crews will install reinforcement steel.
  • Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of November.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of October 31, 2022, crews will install reinforcement steel.
  • During the week of November 7, 2022, crews will install the concrete finishing machine.
  • During the week of November 14, 2022, crews will install the concrete deck.
  • Reinforcement steel for the parapets will install the 3rd and 4th week of November.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of October 31, 2022, crews will complete the demolition of the superstructure for Str. 106.3I and 106.4A.
  • Demolition of Str. 106.3I and Str. 106.4A piers and abutments will take place the rest of November.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late December of 2022 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of November 7, 2022, crews will begin roadway excavation and installation of the roadway box for the crossover.

Traffic Alert – September 27, 2022

Posted on September 27, 2022 by - Traffic Alerts

Traffic Alert – September 27, 2022

Traffic Alert for October 03, 2022:

On or about the night of 10/03/22, Southbound Entrance Ramp will be closed starting at 10:00 PM and will remain closed until May 15, 2023.  This closure is required to replace the superstructure for Str. No.106.3I, Str. No.106.4NO and Str. No. 106.4A. Traffic will be detoured to Route 18 to Route 66 and or to GSP Northbound to Exit 109.  See the “Detours” page for more information on the new traffic patterns. Note that in the event of inclement weather, this work may be rescheduled for the following day 10/04/22 or later until completed. 

Monthly Project Update – September 30, 2022

Posted on September 27, 2022 by - Project Updates

Monthly Project Update – September 30, 2022

Garden State Parkway Exit 105 Monthly Update: 09/30/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of October 28, 2022.

FOUR WEEK SCHEDULE AS OF September 30, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of October 3, 2022, crews will install structural steel utilizing nightly lane closures.
  • During the week of October 10, 2022, crews will install shielding and overhang brackets. 
  • Concrete deck forms, sheer studs, and reinforcement steel will begin the 3rd and 4th week of October.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of October 3, 2022, crews will install deck forms and sheer studs.
  • During the week of October 10, 2022, crews will install reinforcement steel.
  • Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of October.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • On October 3, 2022, the South Bound Entrance Ramp will be closed.  It will remain closed until May 15, 2023.
  • Demolition Str. 106.4A will take place the 1st and 2nd weeks of October utilizing nightly ramp closures.
  • Demolition of Str. 106.3I will take place the 2nd and 3rd weeks of October utilizing nightly lane closures.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of October 3, 2022, work on the SBO to SBI (Local to Express) Crossover is schedule to begin.  Traffic will be shifted both on both the Local and Express lanes to facilitate the construction of this crossover ramp. Work is scheduled to take 4 weeks to construct.