Archive Author: GSPI 105 Project Team

Monthly Project Update – February 01, 2023

Posted on February 1, 2023 by - Project Updates

Monthly Project Update – February 01, 2023

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of February 27, 2023.

FOUR WEEK SCHEDULE AS OF February 01, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 30, 2023, crews will install concrete for parapet for Str. 106.4I.
  • During the week of February 06, 2023, crews will install concrete for parapet for Str. 106.4NO.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The South Bound Inner Exit Ramp is scheduled to open the week of February 20, 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 06, 2023, crews will groove the concrete deck.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The North Bound Inner Entrance Ramp is scheduled to open the week of February 20, 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of February 03, 2023, crews will install structural steel at 106.4A.
  • During the week of February 6, 2023, crews will concrete for abutment reconstructions.
  • Erection of precast concrete units are scheduled for the week of February 13, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin late February of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • During the week of February 06, 2023, crews will roadway striping and move precast concrete construction barrier.
  • Opening of the crossover is schedule for the week of February 13, 2023.  

Monthly Project Update – January 13, 2023

Posted on January 13, 2023 by - Project Updates

Monthly Project Update – January 13, 2023

FOUR WEEK SCHEDULE AS OF January 13, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 16, 2023, crews will install reinforcement steel for parapet.
  • During the week of January 23, 2023, crews will install concrete for Parapet.
  • The South Bound Inner Exit Ramp is scheduled to open the month of February 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of January 23, 2023, crews will install guide rail.
  • During the week of January 30, 2023, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open the month of February 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of January 16, 2023, crews will install concrete for pier and abutments.
  • During the week of January 30, 2023, crews will remove forms in preparation for beam erection.
  • Erection of structural steel and precast concrete units are scheduled for the beginning of February.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • Opening of the crossover is schedule for the month of February 2023.  

Monthly Project Update – December 01, 2022

Posted on December 1, 2022 by - Project Updates

Monthly Project Update – December 01, 2022

FOUR WEEK SCHEDULE AS OF December 01, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of December 05, 2022, crews will install reinforcement steel.
  • During the week of December 12, 2022, crews will install concrete deck.
  • Concrete Parapet will be installed the 4th week of December.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of December 12, 2022, crews will install the concrete Parapet.
  • During the week of December 19, 2022, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open The first week of January 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of December 5, 2022, crews will install anchor bolts for bearings.
  • During the week of December 12, 2022, crews will drill and grout reinforcement steel.
  • Installation of pier forms at Str. 106.3I and Str. 106.4A will take place the rest of December.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of December 12, 2022, crews will install the asphalt surface course.  

Monthly Project Update – October 26, 2022

Posted on October 26, 2022 by - Project Updates

Monthly Project Update – October 26, 2022

Garden State Parkway Exit 105 Monthly Update: 10/26/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted approximately during the week of November 27, 2022.

FOUR WEEK SCHEDULE AS OF October 26, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of October 31, 2022, crews will install forms for the bridge deck.
  • During the week of November 7, 2022, crews will install Joints and shear studs.
  • During the week of November 14, 2022, crews will install reinforcement steel.
  • Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of November.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of October 31, 2022, crews will install reinforcement steel.
  • During the week of November 7, 2022, crews will install the concrete finishing machine.
  • During the week of November 14, 2022, crews will install the concrete deck.
  • Reinforcement steel for the parapets will install the 3rd and 4th week of November.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of October 31, 2022, crews will complete the demolition of the superstructure for Str. 106.3I and 106.4A.
  • Demolition of Str. 106.3I and Str. 106.4A piers and abutments will take place the rest of November.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late December of 2022 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of November 7, 2022, crews will begin roadway excavation and installation of the roadway box for the crossover.

Traffic Alert – September 27, 2022

Posted on September 27, 2022 by - Traffic Alerts

Traffic Alert – September 27, 2022

Traffic Alert for October 03, 2022:

On or about the night of 10/03/22, Southbound Entrance Ramp will be closed starting at 10:00 PM and will remain closed until May 15, 2023.  This closure is required to replace the superstructure for Str. No.106.3I, Str. No.106.4NO and Str. No. 106.4A. Traffic will be detoured to Route 18 to Route 66 and or to GSP Northbound to Exit 109.  See the “Detours” page for more information on the new traffic patterns. Note that in the event of inclement weather, this work may be rescheduled for the following day 10/04/22 or later until completed. 

Monthly Project Update – September 30, 2022

Posted on September 27, 2022 by - Project Updates

Monthly Project Update – September 30, 2022

Garden State Parkway Exit 105 Monthly Update: 09/30/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of October 28, 2022.

FOUR WEEK SCHEDULE AS OF September 30, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of October 3, 2022, crews will install structural steel utilizing nightly lane closures.
  • During the week of October 10, 2022, crews will install shielding and overhang brackets. 
  • Concrete deck forms, sheer studs, and reinforcement steel will begin the 3rd and 4th week of October.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of October 3, 2022, crews will install deck forms and sheer studs.
  • During the week of October 10, 2022, crews will install reinforcement steel.
  • Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of October.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • On October 3, 2022, the South Bound Entrance Ramp will be closed.  It will remain closed until May 15, 2023.
  • Demolition Str. 106.4A will take place the 1st and 2nd weeks of October utilizing nightly ramp closures.
  • Demolition of Str. 106.3I will take place the 2nd and 3rd weeks of October utilizing nightly lane closures.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of October 3, 2022, work on the SBO to SBI (Local to Express) Crossover is schedule to begin.  Traffic will be shifted both on both the Local and Express lanes to facilitate the construction of this crossover ramp. Work is scheduled to take 4 weeks to construct.

Monthly Project Update – August 29, 2022

Posted on August 29, 2022 by - Project Updates

Monthly Project Update – August 29, 2022

Garden State Parkway Exit 105 Monthly Update: 08/29/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 12, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 7, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October 1, 2022, with the full closure of the South bound Entrance Ramp. The entrance ramp will be closed until all bridge structures are replaced.  This is anticipated to be completed May 15, 2022. Three detours will be in place.  See link for detours. 

South Bound Entrance Ramp, Ramp E1

  • On August 26, 2022, a watermain break was found in the South Bound Entrance Ramp.  The cause of the watermain break was not related to current construction activities.  The watermain was repaired and the roadway was restored.  

Monthly Project Update – August 2, 2022

Posted on August 2, 2022 by - Project Updates

Monthly Project Update – August 2, 2022

Garden State Parkway Exit 105 Monthly Update: 08/02/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 02, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 08, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of August 15, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the third week of August.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 22, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of August 29, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October of 2022.

Monthly Project Update – July 8, 2022

Posted on July 8, 2022 by - Project Updates

Monthly Project Update – July 8, 2022

Garden State Parkway Exit 105 Monthly Update: 07/08/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in August, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF July 08, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of July 11, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of July 18, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the last week of July.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of July 18, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of July 25, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.

North Bound Entrance, Ramp E4

  • On July 5, 2022, a sinkhole was found in the North Bound Entrance Ramp.  The cause of the sinkhole was not related to current construction activities.  The sinkhole was filled in and a new drainage pipe was installed in this location. 

Monthly Project Update – May 31, 2022

Posted on May 31, 2022 by - Project Updates

Monthly Project Update – May 31, 2022

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of June 27, 2022.

FOUR WEEK SCHEDULE AS OF MAY 31, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of June 6, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 
  • During the week of June 13, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.