Monthly Project Update – May 25, 2023
Garden State Parkway Exit 105 Monthly Update: 05/25/23
The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of June 12, 2023.
FOUR WEEK SCHEDULE AS OF May 25, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- This stage is considered substantially complete.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- This stage is considered substantially complete.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- The ramp was opened the evening of May 12, 2023.
- This stage is considered substantially complete.
Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit
- During the week of June 5, 2023, crews will install structural steel for the bridge deck.
- During the week of June 12, 2023, crews will install temporary catch and stay-in-place forms.
- During the week of June 19, 2023, crews will begin to install rebar and deck forms.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the day of March 10, 2023, crews opened the crossover to traffic.