FOUR WEEK SCHEDULE AS OF July 31, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- This stage is considered substantially complete.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- This stage is considered substantially complete.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- This stage is considered substantially complete.
Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit
- During the week of July 31, 2023, last pour of deck concrete on Str. 106.4I and continue to work on beam repairs for Str. 106.4SO.
- During the week of August 8, 2023, crews will install reinforcement steel for parapets on Str. 106.4I.
- During the week of August 15, 2023, crews will start to form the parapets on Str. 106.4I.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the day of March 10, 2023, crews opened the crossover to traffic.