Monthly Project Update – June 23, 2023
Garden State Parkway Exit 105 Monthly Update: 06/23/23
The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of July 25, 2023.
FOUR WEEK SCHEDULE AS OF May 25, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- This stage is considered substantially complete.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- This stage is considered substantially complete.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- This stage is considered substantially complete.
Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit
- During the week of June 25, 2023, crews will install stay-in-place forms and joints.
- During the week of July 4, 2023, crews will install reinforcement steel.
- During the week of July 10, 2023, crews will work to install deck concrete.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the day of March 10, 2023, crews opened the crossover to traffic.