Monthly Project Update – April 28, 2023
Garden State Parkway Exit 105 Monthly Update: 04/28/23
The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of May 12, 2023.
FOUR WEEK SCHEDULE AS OF April 28, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- This stage is considered substantially complete.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- This stage is considered substantially complete.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- During the week of May 1, 2023, crews will install roadway subgrade and asphalt for the bridge approaches.
- During the week of May 8, 2023, crews will install guide rail and roadway stripes in anticipation of the ramp opening.
- The ramp is scheduled to be opened May 12, 2023.
Work Area B – Str. 106.4I, Str. 106.4NO and Str. 106.4 SO – Ramp E2, South Bound Outer Lanes Exit
- During the week of May 1, 2023, crews will continue with demolition of piers and wing walls for Str. 106.4I.
- During the week of May 8, 2023, crews will begin with begin with the installation of drill and grout reinforcement steel for Str. 106.4I.
- During the week of May 15, 2023, crews will begin concrete repairs on Str. 106.4SO.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the day of March 10, 2023, crews opened the crossover to traffic.