The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted during the week of May 8, 2023.
FOUR WEEK SCHEDULE AS OF April 13, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- During the week of March 6, 2023, work on Str. 106.4I was completed.
- During the night of March 11, 2023, traffic was opened to the South Bound Inner Exit Ramp.
- This stage is considered substantially complete.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- During the week of February 27, 2023, work on Str. 106.5NO was completed.
- During the night of March 6, 2023, traffic was opened to the North Bound Inner Entrance Ramp.
- This stage is considered substantially complete.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- During the week of April 10, 2023, crews installed parapet concrete at 106.4A and parapet reinforcement at Str. 106.3I.
- During the week of April 17, 2023, crews will install parapet concrete at Str. 106.3I and perform spall repairs at Str. 106.4NO.
- During the week of May 1, 2023, crews will install the parapet for Str. 106.4NO.
- Asphalt is scheduled to be installed the week of May 8, 2023.
Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit
- During the week of April 17, 2023, demolition will begin with saw cutting and removing the superstructure for Str. 106.4I.
- During the week of May 1, 2023, crews will begin demolition of piers for Str. 106.4I.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the week of March 6, 2023, crews finished installation of ground mounted signs.
- During the day of March 10, 2023, crews opened the crossover to traffic.