Monthly Project Update – March 14, 2023

Posted on March 14, 2023 by - Project Updates

Monthly Project Update – March 14, 2023

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in April 2023.

FOUR WEEK SCHEDULE AS OF March 14, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of March 6, 2023, work on Str. 106.4I was completed.
  • During the night of March 11, 2023, traffic was opened to the South Bound Inner Exit Ramp.
  • This stage is considered substantially complete.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 27, 2023, work on Str. 106.5NO was completed.
  • During the night of March 6, 2023, traffic was opened to the North Bound Inner Entrance Ramp.
  • This stage is considered substantially complete.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of March 13, 2023, crews will install reinforcement steel at 106.4A and continue with form work at Str. 106.3I.
  • During the week of March 20, 2023, crews will install concrete for the deck of Str. 106.4A.
  • Closure pours for Str. 106.3I are scheduled for the week of March 27, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • During the night of March 11, 2023, traffic was close to the South Bound Outer Exit Ramp.
  • During the week of March 13, 2023, crews will begin demolition of Str. 106.4I and 106.4NO by removing the asphalt overlay.  

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of March 6, 2023, crews finished installation of ground mounted signs.
  • During the day of March 10, 2023, crews opened the crossover to traffic.