FOUR WEEK SCHEDULE AS OF February 01, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 30, 2023, crews will install concrete for parapet for Str. 106.4I.
  • During the week of February 06, 2023, crews will install concrete for parapet for Str. 106.4NO.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The South Bound Inner Exit Ramp is scheduled to open the week of February 20, 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of February 06, 2023, crews will groove the concrete deck.
  • During the week of February 13, 2023, crews will pave the South Bound Inner Exit Ramp.
  • The North Bound Inner Entrance Ramp is scheduled to open the week of February 20, 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of February 03, 2023, crews will install structural steel at 106.4A.
  • During the week of February 6, 2023, crews will concrete for abutment reconstructions.
  • Erection of precast concrete units are scheduled for the week of February 13, 2023.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin late February of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • During the week of February 06, 2023, crews will roadway striping and move precast concrete construction barrier.
  • Opening of the crossover is schedule for the week of February 13, 2023.