Archive Month: January 2023

Monthly Project Update – January 13, 2023

Posted on January 13, 2023 by - Project Updates

Monthly Project Update – January 13, 2023

FOUR WEEK SCHEDULE AS OF January 13, 2023:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of January 16, 2023, crews will install reinforcement steel for parapet.
  • During the week of January 23, 2023, crews will install concrete for Parapet.
  • The South Bound Inner Exit Ramp is scheduled to open the month of February 2023.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of January 23, 2023, crews will install guide rail.
  • During the week of January 30, 2023, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open the month of February 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of January 16, 2023, crews will install concrete for pier and abutments.
  • During the week of January 30, 2023, crews will remove forms in preparation for beam erection.
  • Erection of structural steel and precast concrete units are scheduled for the beginning of February.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of January 30, 2023, crews will install ground mounted signs.
  • Opening of the crossover is schedule for the month of February 2023.