Monthly Project Update – January 13, 2023
FOUR WEEK SCHEDULE AS OF January 13, 2023:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- During the week of January 16, 2023, crews will install reinforcement steel for parapet.
- During the week of January 23, 2023, crews will install concrete for Parapet.
- The South Bound Inner Exit Ramp is scheduled to open the month of February 2023.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- During the week of January 23, 2023, crews will install guide rail.
- During the week of January 30, 2023, crews will groove the concrete deck.
- The North Bound Inner Entrance Ramp is tentatively scheduled to open the month of February 2023.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- During the week of January 16, 2023, crews will install concrete for pier and abutments.
- During the week of January 30, 2023, crews will remove forms in preparation for beam erection.
- Erection of structural steel and precast concrete units are scheduled for the beginning of February.
Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit
- Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the week of January 30, 2023, crews will install ground mounted signs.
- Opening of the crossover is schedule for the month of February 2023.