Monthly Project Update – December 01, 2022

Posted on December 1, 2022 by - Project Updates

Monthly Project Update – December 01, 2022

FOUR WEEK SCHEDULE AS OF December 01, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of December 05, 2022, crews will install reinforcement steel.
  • During the week of December 12, 2022, crews will install concrete deck.
  • Concrete Parapet will be installed the 4th week of December.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of December 12, 2022, crews will install the concrete Parapet.
  • During the week of December 19, 2022, crews will groove the concrete deck.
  • The North Bound Inner Entrance Ramp is tentatively scheduled to open The first week of January 2023.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • During the week of December 5, 2022, crews will install anchor bolts for bearings.
  • During the week of December 12, 2022, crews will drill and grout reinforcement steel.
  • Installation of pier forms at Str. 106.3I and Str. 106.4A will take place the rest of December.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.

SBO to SBI (Local to Express) Crossover – MP 108.6

  • During the week of December 12, 2022, crews will install the asphalt surface course.