Monthly Project Update – December 01, 2022
FOUR WEEK SCHEDULE AS OF December 01, 2022:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- During the week of December 05, 2022, crews will install reinforcement steel.
- During the week of December 12, 2022, crews will install concrete deck.
- Concrete Parapet will be installed the 4th week of December.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- During the week of December 12, 2022, crews will install the concrete Parapet.
- During the week of December 19, 2022, crews will groove the concrete deck.
- The North Bound Inner Entrance Ramp is tentatively scheduled to open The first week of January 2023.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- During the week of December 5, 2022, crews will install anchor bolts for bearings.
- During the week of December 12, 2022, crews will drill and grout reinforcement steel.
- Installation of pier forms at Str. 106.3I and Str. 106.4A will take place the rest of December.
Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit
- Work in this area is scheduled to begin middle to late January of 2023 after Work Area C is completed.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the week of December 12, 2022, crews will install the asphalt surface course.