FOUR WEEK SCHEDULE AS OF October 26, 2022:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- During the week of October 31, 2022, crews will install forms for the bridge deck.
- During the week of November 7, 2022, crews will install Joints and shear studs.
- During the week of November 14, 2022, crews will install reinforcement steel.
- Concrete finishing machine will be set up and deck concrete will be installed the 3rd and 4th week of November.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- During the week of October 31, 2022, crews will install reinforcement steel.
- During the week of November 7, 2022, crews will install the concrete finishing machine.
- During the week of November 14, 2022, crews will install the concrete deck.
- Reinforcement steel for the parapets will install the 3rd and 4th week of November.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- During the week of October 31, 2022, crews will complete the demolition of the superstructure for Str. 106.3I and 106.4A.
- Demolition of Str. 106.3I and Str. 106.4A piers and abutments will take place the rest of November.
Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit
- Work in this area is scheduled to begin middle to late December of 2022 after Work Area C is completed.
SBO to SBI (Local to Express) Crossover – MP 108.6
- During the week of November 7, 2022, crews will begin roadway excavation and installation of the roadway box for the crossover.