Monthly Project Update – August 2, 2022

Posted on August 2, 2022 by - Project Updates

Monthly Project Update – August 2, 2022

Garden State Parkway Exit 105 Monthly Update: 08/02/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 02, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 08, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of August 15, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the third week of August.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 22, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of August 29, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October of 2022.