Archive Month: August 2022

Monthly Project Update – August 29, 2022

Posted on August 29, 2022 by - Project Updates

Monthly Project Update – August 29, 2022

Garden State Parkway Exit 105 Monthly Update: 08/29/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 29, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 12, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 29, 2022, crews will finish the removal of concrete form work and install bearings
  • During the week of September 7, 2022, crews will begin to installation of structural steel utilizing nightly lane closures.
  • Concrete deck forms and reinforcement steel will begin the 3rd and 4th week of September.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October 1, 2022, with the full closure of the South bound Entrance Ramp. The entrance ramp will be closed until all bridge structures are replaced.  This is anticipated to be completed May 15, 2022. Three detours will be in place.  See link for detours. 

South Bound Entrance Ramp, Ramp E1

  • On August 26, 2022, a watermain break was found in the South Bound Entrance Ramp.  The cause of the watermain break was not related to current construction activities.  The watermain was repaired and the roadway was restored.  

Monthly Project Update – August 2, 2022

Posted on August 2, 2022 by - Project Updates

Monthly Project Update – August 2, 2022

Garden State Parkway Exit 105 Monthly Update: 08/02/22

The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis through the end of 2023. The next update will be posted in September, 2022. Questions about the project can be directed to the Project Team via the Contact Form, HERE.

FOUR WEEK SCHEDULE AS OF August 02, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of August 08, 2022, crews will begin on Str. 106.4I installing reinforcement steel at the piers and abutment. 
  • During the week of August 15, 2022, crews will begin to installation of form work for the new bearing pedestals.
  • Concrete placement for the new pier caps is scheduled to begin the third week of August.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of August 22, 2022, crews will begin on Str. 106.5NO installing reinforcement steel at the piers and abutment. 
  • During the week of August 29, 2022, crews will begin to installation of form work for the new bearing pedestals.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the October of 2022.