FOUR WEEK SCHEDULE AS OF MAY 31, 2022:

Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit

  • During the week of June 6, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance

  • During the week of May 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts. 
  • During the week of June 13, 2022, crews will begin on Str. 106.4I to preform selective demolition to pier caps. 
  • The demolition of the pier caps will be followed by the forming and installation of reinforcement steel for the modification of the piers cap elevations.

Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit

  • Work in this area is scheduled to begin in the Fall of 2022.

Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance

  • Work in this area is scheduled to begin in the Fall of 2022.