Monthly Project Update – April 29, 2022
The message below contains important project updates for the GSP Interchange 105 Improvement Project and will be posted on a monthly basis, during the last week of the month, through the end of 2023. The next update will be posted during the week of May 25, 2022.
FOUR WEEK SCHEDULE AS OF APRIL 29, 2022:
Work Area C – Str. 106.4I & Str. 106.4NO – Ramp E3, South Bound Inner Lanes Exit
- During the week of May 2, 2022, work will begin on Str. 106.4I to prepare for the removal of the superstructure.
- During the week of week of May 16 and 23, 2022, crews will remove the superstructure (deck and beam) of Str. 106.4I. Weather permitting, this work is anticipated to take 6 shifts.
Work Area D – Str. 106.5NO – Ramp E7, North Bound Inner Entrance
- During the week of May 9, 2022, work will begin on Str. 106.5NO to prepare for the removal of the superstructure.
- During the week of May 23 and 31, 2022, crews will remove the superstructure (deck and beam) of Str. 106.5NO. Weather permitting, this work is anticipated to take 3 shifts.
Work Area B – Str. 106.4I & Str. 106.4NO – Ramp E2, South Bound Outer Lanes Exit
- Work in this area is scheduled to begin in the Fall of 2022.
Work Area A – Str. 106.3I, Str. 106.4NO and Str. 106.4A – Ramp E1, South Bound Entrance
- Work in this area is scheduled to begin in the Fall of 2022.